SUEZ Steel – Maintenance Shutdown

Rectangle 20

Project Data & EL-Mahd Responsibility

The Suez Steel group is one of the largest steel making plants in Egypt, located on Suez – Egypt., El-Mahd performed several construction activities as mentioned before for Suez Steel Complex on the DRP unit and SMP1.

The Scope Of Work

El-Mahd achieved the project construction completion target supported with a professional documentation record and reporting by the planned project schedule the matter which build up a trust relationship with the project contractor/client, based on this trust the client recommended El-Mahd to perform several maintenance activities during normal scheduled shut-downs, following the main activities performed by El-Mahd :
Providing Qualified Technicians for maintenance shut-down assignments.
Various modification on the PG Heater convective section.
Machinery services and special fit-up tools supply.
PQR and WPS for the required material.
Fit-up and welding the new 288 joints.
Provide the required lifting tools/equipment.
Provide the required generator for the activities.
Provide the required scaffolding.
Provide all of the special tools for cutting and welding.
Provide argon gas and all of the consumables.

Project Gallery

Release Date

April 2014

Client

SUEZ steel Co.

Main Contractor

DANIELI Middle East for Engineering Services MEES

Location

Suez - Egypt